Happy Holidays & Winter Coastal Updates

Off

Vanishing Paradise newsletter

Winter Update

Ongoing construction at levee-highway crossing in lower Golden Meadow.

Building Increased Resiliency in Highway Infrastructure
LA-1 Elevated Highway Construction

…And…
Fourchon-To-Grand Isle Armoring

Two projects pertaining to LA-1 that will certainly improve our resiliency following future storms include the completion of the LA-1 Elevated Highway between Golden Meadow and Fourchon …AND… the completion of an Entergy Project to place over 7 miles (primarily between Fourchon and Grand Isle) of high-voltage cable underground.
With construction expected to be complete by July of 2027, this last segment of highway will allow our port authorities and those who utilize the port for offshore energy services to get back up and running in even shorter time than before following hurricanes, as well as keep traffic flowing during the occasional high-water events. Click the above ‘LA-1″ title for more information.
Immediately following the aftermath of Hurricane Ida, Entergy ran subterranean, high-voltage power cables along the northside LA-1 between Dogris and Thunder Bayou. As part of their agreement with LA-DOT, Entergy went back and revamped the shoulder-area with rocks and covered it with a slurry of concrete to hold it in place along the entire length of the cable-lay.  This new style of hardened armoring along with the Class-1 power-poles (placed within hammer-driven caissons and filled with rock should provide us a new level of power-transmission resiliency that we have not seen before.  Click on the ‘Fourchon-To-Grand Isle’ link for more information.

Video Highlighting Entergy’s Fourchon-To-GrandIsle Improvements

Click Image For More Information

Caminada Headlands Back Marsh Creation Project

Caminada Headlands Back Marsh Creation Project, Fourchon Road (foreground) looking eastward towards Elmer’s Island & Grand Isle,

Caminada Headlands Project Completes

The EPA-sponsored Caminada Headland Back Barrier Marsh Creation project began in June 2020 and the dredging was completed just few weeks ago.
Working with the Louisiana Coastal Protection and Restoration Authority (CPRA) and EPA, the contractor – Great Lakes Dredge & Dock Corporation (GLDD) has created approximately 900 acres of coastal habitat in southeast Louisiana.  If one takes an airboat tour from the far west end nearest to the Fourchon Beach Access Road and traveles (nearly 7 miles!) all the way to Elmer’s Island end of the project, one really gets an idea of just how big this project is.  

View Details & a Video of the Project Here at EPA.gov

Cheniere Breakwaters in Caminada Bay

View from atop Grand Isle Bridge showing Cheniere Breakwater Project & two Rigid Constructor cranes.

Grand Isle Beach & Cheniere Breakwater Projects Continue

Following hurricane Ida, a 4-phase plan was made to improve Grand Isle and it’s surrounding area.
Phase-1 was to work on the beachside set of breakwaters on the far west end of the island and extend the first set of rocks (western-most, closest to Caminada Pass) all the way to the jetties that form the eastside of the pass; and this work was completed late in the summer of 2022.
Phase-2 is to build 5 segmented breakwater jetties on the northern side of Caminada Bay to protect the Cheniere side.  This work started early in the Fall of 2022 is currently nearing completion with only the western-most set of breakwaters left to complete. [If you notice a different color of rocks now being placed, that is due to the historic low levels of the Mississippi River that is making it difficult to get rocks from the planned quarry and instead now being sourced from an alternative quarry.]
Phase-3 is to fix all the breeches in the Grand Isle dune (burrito) levee, achieve a uniform profile across the length of the island, and lastly to add sand via hydraulic dredging where necessary.  This work is currently underway in ‘skip around’ fashion.
Phase-4 is to eventually to spend the remainder of the $120 million allocated to place segmented breakwaters (similar to those on the eastern half, as well as the 5 on the western end) across the remainder of the island.  This project is likely not 
to begin until after the 2023 hurricane season.

View a PDF of the Chenier Breakwater Project Plans

CRCL Volunteers & employees build an oyster reef at Bayou Pointe-au-Chien near Montegut, LA

Oyster Shell Recycling Projects In Terrebonne Parish

This is the second reef CRCL and its volunteers have built with the Pointe-au-Chien Indian Tribe, whose community in Lafourche and Terrebonne parishes was hit hard by Hurricane Ida in 2021. The oyster reef will help slow erosion as well as create habitat for new oysters and other wildlife, and it will minimize storm surge during hurricanes, protecting the community.  The reef was constructed in late September and early October with the help of more than 150 volunteers.

Read more about this project

Sunset over West Grand Terre following the staging for RoR’s Planting Event

WGT Group Photo

Volunteer Group Photo following a successful  planting on West Grand Terre 

 

West Grand Terre Planting Event — Saturday, November 12, 2022

One of the ambitious projects that Restore Or Retreat took on in 2022 was to compliment the great work done by CPRA’s dune nourishment project on West Grand Terre by organizing 30 volunteers to travel by boat and plant over 7,500 Vermillion Smooth Cord Grass plugs and 516 Black Mangroves in a 10-acre area on the north/bay side of the island in order to preserve the unique topography of small cuts and inlets that had formed and already began providing habitat for small bait fish and larger gamefish predators.

See our short video   See our photo album


Follow Us On:
Facebook      Twitter      Instagram

© 2022 Restore or Retreat, Inc. 
P.O. Box 2048-NSU, 322 Audubon, South Babington, Thibodaux, LA 70310
Learn more about us at: www.RestoreOrRetreat.org